| Contact |
| Login
Machining, Fabrication and Installation

Part 3: Fixing non-metallic linings: field installation techniques

phan 3 tru 4

A non-metallic lining may be made from the correct material but can still detach, fall off or separate from the supporting structure if the fixing method is unsuitable.

For this material group, the failure point is often not the lining itself, but the attachment between the lining and the supporting structure.

With adhesive bonding in particular, even a small area with insufficient adhesive at a tile corner can become the starting point for detachment.

For this reason, installation needs to control substrate preparation, fixing method, installation procedure, mandatory waiting times and signs that can be checked directly in the field.

1. Explanation of key technical terms used in this article

The following terms appear throughout the selection, installation and inspection of non-metallic linings.

Five terms directly related to lining fixation

Technical term Meaning
Lining A wear-resistant material layer fixed to the supporting structure
Peel An unfavorable loading mode in an adhesive joint, typically occurring at lining corners
Shear in an adhesive joint A more favorable loading mode, typically occurring in the central area of a tile or plate
Mandatory waiting time Required material waiting time that cannot be shortened simply by increasing manpower
Expanded metal mesh Steel mesh fixed to a wall to retain cast, trowelled or sprayed lining material

In addition to the fixing mechanism, non-metallic linings also involve several terms related to how the material performs on the equipment.

Technical term Meaning
Slide promotion Helping bulk material slide instead of adhering to the surface
Material adhesion Bulk material accumulates on the surface and obstructs flow
Interface Location where two material groups meet on the same component
Upper temperature limit Temperature above which the material group loses the required operating properties

In this article, the term lining is used instead of coating.

The word coating may suggest a thin paint-like layer, while this article refers to wear protection systems that are fixed to or formed on a supporting structure using several different mechanisms.

2. Four fixing methods and how to select them

Non-metallic linings are not fixed to the supporting structure using a single method.

Site conditions, equipment geometry, temperature, impact, removal requirements and accessibility can all affect the fixing solution.

2.1. Four main fixing methods

No. Fixing method When used Common mistake Possible consequence
1 Monolithic casting, trowelling or spraying Large areas, complex geometry, fewer joints required, on-site repair required Incorrect mesh spacing or incorrect distance between mesh and wall Lining may separate from the substrate
2 Rear-side weld studs Removable lining required, thin plates Stud head exposed to material flow Stud head may wear first and the lining may loosen
3 Adhesive bonding Flat surface, suitable temperature, no severe impact Insufficient adhesive at the four corners Detachment starts from the corners
4 Welded steel rings Impact resistance required, higher-temperature conditions Unsuitable tack welding Lining may crack due to heat

The order above reflects the frequency of occurrence in the project records used as the source. It is not a general industry usage ranking.

One advantage of monolithic systems in suitable locations is the reduction in the number of joints.

Joints are locations where material flow can act directly on gaps or edges. Therefore, where geometry and operating conditions allow, reducing the number of joints also reduces one group of potential failure points.

2.2. Selecting the method according to actual conditions

The table below provides initial guidance before detailed design and installation.

Condition Method to consider
Large area, complex geometry Monolithic casting
Removal required for maintenance Weld studs
Flat surface, suitable temperature, no severe impact Adhesive bonding
Severe impact Welded steel rings or consider another material group
High temperature Monolithic lining or a suitable mechanical fixing solution
Thin plate, adhesive bonding not possible Weld studs

This table is intended for initial guidance and does not replace assessment of the actual site conditions.

A single field condition can eliminate an entire fixing method. For example, if there is no rear-side access, a weld-stud solution may no longer be practical even if the other conditions are suitable.

3. Corner detachment is directly related to the loading state of the adhesive joint

At the center of a lining tile, the load is distributed over a larger area and the adhesive is mainly subjected to shear.

At the corner, the condition changes. The adhesive is subjected to peel from multiple directions, which is a less favorable loading mode for the bonded joint.

Insufficient adhesive at a corner therefore does more than reduce a small portion of the bonded area. The void occurs precisely in a sensitive area of the joint.

Even a corner area without adhesive that is only about the size of a fingertip can become the starting point for the entire tile to detach after a period of operation.

When a lining falls off, the attachment between the lining and the supporting structure should be checked before concluding that the lining material itself is defective.

4. Monolithic casting, trowelling or spraying

With monolithic methods, bond quality depends directly on substrate preparation, mesh arrangement, material mixing and curing control.

4.1. Substrate preparation, mixing and installation

Control item Requirement
Steel substrate preparation Weld expanded metal mesh to the wall, with a 3 to 5 mm gap from the wall for a 20 to 25 mm lining thickness, and mesh-retaining weld points spaced 250 to 300 mm apart
Concrete substrate preparation Do not use the same preparation method as for steel walls; the surface needs to be thoroughly wetted before trowelling
Dry mixing Forced-action mixer at 40 rpm; dry mix powder and reinforcing fibers for at least 1 minute before adding water
Mixing water 10 to 25 °C, quantity according to the exact material grade
Wet mixing 4 to 8 minutes depending on the material system
Installation temperature 10 to 30 °C; stop installation if the structure or ambient air is below 5 °C
After finishing Seal in moisture within 60 minutes after finishing
Cold curing Minimum 24 hours at 20 °C before drying
Acceptable sign Continuous lining, no voids, solid sound when lightly tapped
Sign requiring corrective action Hollow sound when tapped, indicating a void or unsuitable bonding area

One issue that needs to be controlled from the preparation stage is mesh positioned directly against the wall.

If the required gap is lost, the material may not fully penetrate behind the mesh. The base of the lining may then fail to form correctly and become a location where separation from the substrate begins.

Values such as mesh spacing, water quantity, mixing time and installation conditions must be checked against the exact material grade being used.

4.2. Moisture sealing after finishing

After the surface is finished, the lining needs to be moisture-sealed within the specified period.

If the surface begins to dry before this step is performed, water retention during curing may be affected.

This is a mandatory waiting point governed by the material reaction. Adding more manpower does not make this process occur faster.

4.3. Three requirements that need to be determined before mixing

Divide the installation area

Large surfaces should be divided into installation sections rather than completed continuously as one large area.

The material shrinks during curing. Dividing the area helps control where stress accumulates.

Provide expansion joints

According to the documentation being used, where the operating temperature exceeds 50 °C, an expansion joint should be provided with a 5 mm rigid foam strip.

The reason is the difference in thermal expansion between the steel structure and the lining. The two materials do not change dimensions at the same rate as temperature changes.

The reinforcing steel mesh must be cut along the joint line. If the mesh remains continuous across the joint, stress continues to transfer into the adjacent area and the joint cannot perform its intended function.

Provide edge-retaining strips

At the boundary between lined and unlined areas, as well as at termination edges, a suitable steel retaining strip should be provided.

If the lining tapers down toward the edge, that location can become the starting point for detachment.

5. Initial heat-up curve after installation

For heated equipment, once the material has completed the required cold-curing period, the first heat-up should not go directly to operating temperature.

Stage Rate and hold point
Initial heat-up Maximum 40 °C/hour up to 150 °C
Holding Hold at 150 °C for 12 hours
Further heat-up Maximum 100 °C/hour up to operating temperature
Subsequent operation Above 150 °C, maximum temperature change of 40 °C/hour

The 12-hour holding period needs to be included in the operating plan.

If the temperature rises too quickly while moisture remains inside the lining, steam may form suddenly and cause explosive spalling during the first start-up.

The schedule therefore needs to include:

  • cold-curing time
  • drying time
  • holding time
  • heat-up time to operating temperature

Actual installation duration includes more than only the time spent trowelling or spraying the material.

6. Rear-side weld studs

With this method, control points focus on connection dimensions, weld condition and the position of the bolt or stud head relative to the working surface.

Control item Requirement
Method Weld the stud foot to the rear side of the backing plate, then install and tighten the lining plate
Anchor diameter Minimum 12 mm
For diameters above 12.5 mm Manual welding around the stud foot using low-hydrogen welding consumables
Plug welding through holes Minimum hole diameter 25 mm, hole spacing 300 to 600 mm
Plug-weld limit Weld metal stops at least 3 mm below the hard-facing interface
Tightening torque Refer to stud size and applicable documentation
Acceptable sign Stud head lies below the working surface and cannot be felt protruding
Sign requiring corrective action Stud head is exposed to material flow

The 3 mm clearance at the plug-weld location is an important control point.

If the weld metal extends too high and mixes into the hard-facing area, the interface can become a location that wears faster than the surrounding surface.

7. Adhesive bonding

For adhesive bonding, mixing, adhesive thickness, usable time and, especially, full coverage at all four corners of the lining tile need to be controlled together.

7.1. Mixing, spreading and laying the tiles

Control item Requirement
Mixing ratio Two components at 1:1 by weight
Mixing time Stir slowly for 5 to 10 minutes, scraping material up from the bottom of the tray
Acceptable mixing sign Adhesive becomes a single uniform color and flows in a continuous stream when the tool is lifted
Sign requiring corrective action Continue mixing if color streaks remain; discard if the adhesive forms strings; do not add solvent
Adhesive application Apply to the rear side of the tile in one direction and fully cover all four corners
Acceptable application sign Tile material is not visible through the adhesive; test lifting shows uniform adhesive contact at all four corners
Deviation requiring attention Voids at the corners
Adhesive thickness 3 mm notched trowel; final adhesive film after pressing remains 2 to 3 mm
Pot life Use within 45 minutes after mixing
Waiting time before nearby welding Minimum 2 hours before placing steel washers and tack welding
Tile arrangement Stagger joints between rows; do not align joints continuously

Full adhesive coverage at the four corners is particularly important because these are the areas where the bonded joint is subjected to peel.

7.2. The 45-minute and 2-hour limits apply to different activities

The 45-minute limit is the pot life of the adhesive batch after mixing.

The 2-hour limit is the minimum waiting time before welding near the newly bonded area.

If the batch is mixed in too large a quantity, the adhesive may exceed its pot life before installation is complete.

If welding is carried out too early to shorten the schedule, heat from welding may affect the adhesive before it has had sufficient time to stabilize.

The batch size should therefore match the area that can be completed within the adhesive pot life, while nearby welding should be scheduled for the following stage.

8. Welded steel rings

This method uses short tack welds with cooling intervals to limit heat input to the surrounding material.

Control item Requirement
Method Use short tack welds and allow cooling between welds
Tack-weld length Refer to the applicable documentation
Cooling time between welds Refer to the applicable documentation
Acceptable sign No cracking around the steel ring; ring remains secure when moved by hand
Sign requiring corrective action Material cracks around the ring after thermal exposure

If cracking appears around the welded location, the connection needs to be handled according to the applicable procedure.

The fact that the steel ring remains attached to the structure is not, by itself, enough to conclude that the location is acceptable.

9. Mandatory waiting times cannot be shortened simply by increasing manpower

The four fixing methods include steps that depend on material reaction or stabilization.

Important waiting periods include:

  • adhesive pot life
  • waiting time before nearby welding
  • curing time
  • moisture-sealing time
  • drying and holding time

These periods cannot be shortened simply by increasing the number of workers.

If available downtime is shorter than expected, the work scope should be reconsidered rather than shortening mandatory material waiting periods without technical justification.

Waiting times therefore need to be identified during installation planning, not after work has already started.

10. Items that can be checked after installation without removing the lining

The four fixing methods allow several simple checks to be performed directly in the field.

Method Inspection method Sign requiring corrective action
Monolithic casting, trowelling or spraying Lightly tap the surface Hollow sound
Rear-side weld studs Run a hand across the lining surface Protruding stud head can be felt
Adhesive bonding Tap along the tile edge Edge sound differs clearly from the center
Welded steel rings Move the ring by hand Ring is loose or cracking appears around it

These inspections do not require lining removal and can help identify certain attachment deviations before the equipment returns to operation.

However, the result only reflects the connection condition at the time of inspection. It is not a method for predicting the final service life of the lining.

11. Acceptable signs and corrective-action signs should be described in observable terms

An installation instruction is only truly usable in the field when the person performing the work can determine what constitutes an acceptable condition and what requires correction.

For example, an instruction such as “mix the adhesive thoroughly” is not sufficient for verifying the operation.

It should state:

  • how long to mix
  • the color of the mixture after mixing
  • how the adhesive behaves when the tool is lifted
  • signs indicating that the adhesive batch is no longer usable

This approach converts installation experience into observable criteria that installers, supervisors and engineering personnel can inspect and compare together.

The same principle applies to hollow sounds in monolithic linings, protruding stud heads and the condition of steel rings after welding.

12. Responsibilities during lining installation

Each stage should have a clearly defined responsible party so that the material solution and actual installation conditions are considered together.

Task Responsible person or team
Select the fixing method Engineering team, based on site conditions
Confirm that the method can be implemented at the actual location Installation team
Confirm that available downtime accommodates the mandatory waiting periods Operations supervisor
Carry out post-installation inspection Installation team, immediately after completion
Evaluate corrective action when hollow-sounding areas are identified Engineering team

A solution may be appropriate from a material perspective but still incomplete if the fixing method cannot be implemented under the actual accessibility conditions.

Installation feasibility therefore needs to be confirmed before the solution is finalized.

13. Scope of application and references

Most numerical thresholds in this article are taken from manufacturer installation guidelines for lining materials, including:

  • mixing ratio
  • adhesive pot life
  • moisture-sealing time
  • anchor-mesh spacing
  • anchor dimensions and spacing

Three parameter groups have intentionally not been assigned fixed values:

  • mesh spacing and spraying productivity for each grade
  • tightening torque by bolt size
  • tack-weld length and cooling time between welds

These parameters must be checked against the exact material and applicable instructions rather than filled in using estimates.

Three additional points should be noted when applying this article.

First, numerical thresholds vary by material. During installation, the documentation for the actual product being used must be consulted.

Second, post-installation inspections can identify certain attachment deviations at the time of inspection but do not determine the final service life of the lining.

Third, this article explains how to select a fixing mechanism and control installation. It does not determine which material group is the most suitable for a specific location.

The peel mechanism at tile corners is used to explain the loading state of bonded joints. Acceptable signs, corrective-action signs, work organization and post-installation inspection practices are based on Gia Anh’s field installation experience.

Share:
Request Solution Consultation
Contact Gia Anh

Request Solution Consultation

Speak directly with our experienced engineers for a free site assessment and consultation on the most suitable solution

Key Clients

Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh
Logo khách hàng tiêu biểu Gia Anh

Table of Contents

Zalo Facebook

Xin chào bạn!
Nhằm bảo vệ quyền lợi của khách hàng, nội dung trên website hiện không hỗ trợ sao chép.
Mong bạn thông cảm và liên hệ với chúng tôi nếu bạn cần sử dụng các nội dung ở đây.